The project is expected to be completed in a total of 30 months
and is divided into three distinct stages:

Ι) Research Stage
Αctions will be designed and implemented to support research and future product design and development (phase II). This stage is divided into the following sections:
Work Unit 1: Defining the Framework for the Application Development
Duration: Month 1 – 9
Description: Implementation of research on the needs and requirements of Telogleio.
Deliverable: D1.1 Study of user requirements and Operational specifications of the applications (M9)
Research Stage Research Stage
ΙΙ) Design & Development Stage

Actions will be planned and implemented for the design and development of applications. This stage is divided into the following sections:

Work Unit 2:Definition of Technical Specifications – Application design
Duration:Month 3 – 12
Description: Technical design of the project: visualization of the operation of the information systems through modeling of use cases and similar diagrams. Physical architecture will be defined.
Deliverable:D2.1 Information Systems Design (M12)
Work Unit 3:Development of Pilot Applications
Duration:Month 7 – 24
Description: At this stage, the applications will be piloted
Deliverable:

D3.1: Pilot version of the artwork display application and creation of QR – Artwork Codes (M24)

D3.2: Pilot version of the digital 3D imaging platform (M24)

D3.3: Pilot version of the educational multimedia games platform (M24) D3.4: Pilot 3D printing of exhibits (M24)

Design & Development Stage Design & Development Stage
III) Pilot installation – Dissemination of project results
The pilot installation of all applications in the premises of Tellogleio will take place. In addition, specific actions will be carried out to support the stage of dissemination of project results. The work sections will be:
Work Unit 4: Control, Pilot Implementation and Validation
Duration: Month 17 – 28
Description: The pilot installation of all systems will be checked and validated.
Deliverable: D4.1 .: Test and Validation Report (M28)
Work Unit 5: Development of final versions of applications
Duration: Month 19 – 30
Description: Development of the final versions of the applications, based on the observations of the tests and the validation report.
Deliverable: D5.1: Final version of the application for the display of works of art and production of QR-Code (M30) D5.2: Final version of the digital 3D imaging platform (M29)  D5.3: Final version of the application of educational multimedia games (M30) D5. 4: Final 3D printing of exhibits (M29) D5.5: User guides (M30)
Work Unit 6: Dissemination of project results
Duration: Month 4 – 30
Description: Dissemination activities like events for target audience, printed and electronic material, website of the project etc
Deliverable: D6.1: Website of the project (M12) D6.2: Report on the dissemination actions (M30) D6.3: Publications of the results of the project (M30) D6.4: Final report of the demonstration of product applications (M30)
Pilot installation - Dissemination of project results Pilot installation - Dissemination of project results

ΠΑΡΑΔΟΤΕΑ

Το έργο προβλέπεται να εκπονηθεί συνολικά σε 30 μήνες και χωρίζεται σε τρία διακριτικά στάδια:

  1. το στάδιο της έρευνας

  2. το στάδιο του σχεδιασμού και της ανάπτυξης

  3. το στάδιο της πιλοτικής εγκατάστασης & διάδοσης αποτελεσμάτων έργου.

 
1. Αρχικά θα σχεδιαστούν και θα υλοποιηθούν ενέργειες για την υποστήριξη της έρευνας και για τον μελλοντικό σχεδιασμό και την ανάπτυξη (στάδιο ΙΙ) των προϊόντων. Το παρόν στάδιο χωρίζεται στις ακόλουθες ενότητες εργασίας:

2. Στάδιο Σχεδιασμού & Ανάπτυξης

Θα προγραμματιστούν και θα υλοποιηθούν ενέργειες για τον σχεδιασμό και την ανάπτυξη των εφαρμογών. Το παρόν στάδιο χωρίζεται στις ακόλουθες ενότητες εργασίας: